CRA conformity assessment routes — and the notified body bottleneck nobody has priced in
Four product tiers, three assessment modules, and one dependency that is not under your control. How the routes work, which products can self-assess, and why the 2027 constraint is capacity rather than engineering.
Michael Parkadze · Software Engineer

On this page
The CRA's conformity routes follow a pattern anyone who has done CE marking will recognise, with one structural difference from the RED that catches people out: the product class decides the route independently of which standards you applied.
Under the RED, applying the harmonised standards in full gets you self-assessment, always. Under the CRA, a product in Annex III class II needs a notified body even with harmonised standards fully applied. Class is destiny, and classification is therefore the first thing to do.
The routes
Article 32 of Regulation (EU) 2024/2847 sets out the procedures, detailed in Annex VIII.
| Tier | Route | Notified body |
|---|---|---|
| Default | Internal control (Module A) | No |
| Important class I | Module A if harmonised standards, common specifications or a European cybersecurity certification scheme are applied in full. Otherwise EU type examination plus conformity to type (Module B+C), or full quality assurance (Module H) | Conditional |
| Important class II | Module B+C, or Module H, or a European cybersecurity certificate at assurance level at least substantial | Yes, in effect |
| Critical (Annex IV) | As class II, and where a delegated act requires it, a European cybersecurity certificate under a scheme at assurance level at least substantial | Yes |
Three things worth drawing out.
Module A is not nothing. Internal control means you assess the product against Annex I yourself, compile the technical documentation in Annex VII, draw up the EU declaration of conformity and affix the CE marking. The work is the same work; what you save is a third party's review of it. Teams hearing "self-assessment" and relaxing have misread which half is the expensive half.
Class I's conditional route has an unmet precondition. The condition is that harmonised standards, common specifications or a certification scheme are applied in full. As of now, no CRA harmonised standard has been cited in the Official Journal, no common specifications have been adopted, and the certification schemes under Regulation (EU) 2019/881 that would substitute are not in place for this purpose. So for the moment the class I self-assessment door is described but not open. Where the standards stand has the detail.
Annex IV's certification requirement is conditional on a delegated act. The regulation gives the Commission power to require European cybersecurity certification for critical products. Until such an act exists, critical products follow the class II routes. This is one of the places where "what the CRA requires" genuinely depends on something that has not happened yet.
What a notified body actually does
Under Module B, a notified body examines the technical documentation and the product type, assesses conformity with the applicable Annex I requirements, and issues an EU type examination certificate. Module C then covers production: you ensure the manufactured products conform to the approved type. Module H instead approves your quality system across design and production, with surveillance.
The choice between B+C and H is mostly about volume and product families. H costs more up front and less per product; it also means a notified body auditing your development process, which is a different kind of engagement from a product review.
For a company doing this once, B+C. For a company with a dozen product lines on a shared platform, H starts to make sense, and the CRA's process requirements in Annex I Part II — which are about your organisation rather than any one product — make the quality-system route more natural than it was under the RED.
The bottleneck
Here is the part worth planning around, and it is not a technical problem.
CRA Chapter IV — the rules on notifying conformity assessment bodies — applied from 11 June 2026. That is when member states became able to designate notified bodies for the CRA. Full application is 11 December 2027. So the entire designation pipeline, and then the entire assessment workload for every important class II and critical product on the EU market, has to fit into roughly eighteen months.
Three observations follow.
Designation takes time, and it has to happen before your assessment can. A notified body has to be accredited and notified for the CRA specifically; existing RED notified bodies are not automatically CRA notified bodies. The pool available in early 2027 will be smaller than the pool in late 2027, and the work does not spread itself evenly.
Demand is concentrated at the deadline. Every manufacturer who treats 11 December 2027 as the date to be ready by will be in the queue in the second half of 2027. The arithmetic of that is not favourable.
Your leverage is the quality of what you submit. You cannot create notified body capacity. You can be the submission that goes through in one round rather than four. That means the technical documentation is complete, the Annex I assessment has a basis for every conclusion, and the evidence is dated and version-matched. The same discipline that shortens a RED notified body engagement applies here, with more at stake.
If anything you sell is class II or critical, the useful action this quarter is to talk to a notified body about their CRA designation status and their 2027 calendar. Not to engage them — to find out whether they will exist for this purpose and when they will have capacity. That conversation is free and it will change your plan.
A sequencing that respects the dependencies
For a manufacturer with a mixed portfolio:
- Classify everything. One page per product. Cheap, stable, and it tells you which products have a third-party dependency.
- For class II and critical products, open the notified body conversation now. Designation status, capacity, what they want to see. This is the long-lead item.
- For class I products, build as if harmonised standards will exist and watch the Official Journal. The EN 40000 horizontal series is the thing to track. If nothing is cited in time, class I products fall to the notified body route too, which changes the capacity arithmetic considerably.
- For default products, the whole job is Annex I and Annex VII. No external dependency, no queue. Do not let the absence of a deadline-forcing third party push this to the end.
- Build the Annex I Part II process regardless of tier. Vulnerability handling, disclosure, SBOM, update distribution. It is tier-independent, it is the longest engineering lead time, and it is the half of Annex I that cannot be done in a quarter.
Step 5 is the one I would start first if I could only start one. Everything in Part II is a running process with organisational dependencies, and none of it can be compressed at the end. The product requirements in Part I are a design review; the process requirements in Part II are a change in how the company operates.
What this does not settle
Two open questions, stated as open rather than answered.
Whether a European cybersecurity certificate will be a practical substitute. The regulation allows certification under Regulation (EU) 2019/881 schemes to stand in for the notified body routes, at assurance level at least substantial. Whether the relevant schemes and implementing acts will be in place in time to be useful is a live question, not a settled one.
How the class I precondition is read if standards arrive late. "Applied in full" is doing a lot of work in a sentence whose object may not exist until 2027. Whether partial availability of a standards series is enough to open the Module A route for a product it covers is the kind of question that gets answered by guidance rather than by the text.
Both are worth watching rather than guessing at, and neither should stop you doing steps 1, 4 and 5.
Primary sources: Regulation (EU) 2024/2847 Article 32 for the procedures, Annex VIII for the modules, Article 7 and Annexes III and IV for the classes, Chapter IV for notified bodies, and Article 71 for the dates. The modules follow the standard Decision No 768/2008/EC pattern, so if you have done CE marking under another directive the shapes will be familiar.